小管道,大工程,思易哲科技不负所托!Small Pipes. Major Projects. Siyizhe Tech: Worthy of Your Trust.

2023-04-27 14:29

2023年2月28日,受金华兰溪某污水处理厂委托,思易哲科技派出三名施工人员前往现场进行污水管道防磨防腐修复。

On February 28, 2023, commissioned by a wastewater treatment plant in Lanxi, Jinhua, SYZO dispatched a three-man crew to the site for anti-wear and anti-corrosion repair of the sewage pipeline.

QQ图片20230425141657.jpgQQ图片20230425141752.jpg

该污水管道位于地下5米,全长60米,直径仅0.7米,主要功能是连通污水厂的曝气生物池和紫外线消毒池。经过长时间的污水和化学材料冲刷,管道内壁已出现大量穿孔且布满汽蚀,甚至有部分已经有渗水现象。如果要将管道全部更换,则需要从头开挖,耗费大量时间和人力物力。了解到客户的需求,早在2月初,我公司技术人员就到污水厂进行拜访和设备试做,污水厂方面认为我公司的碳化硅管道防腐修复技术可以有效延长管道的使用寿命,且成本远低于更换全新的管道。

技术人员根据以往积累的丰富的电厂脱硫管道修复经验,结合污水管道的实际工况,为其制定了不同的修复方案——由于管道排放的大多是含化学成分的污水,易造成汽蚀,且管道内多处穿孔渗水,无法直接进行修复,因此本次修复采取“先堵漏,后防磨”的方案。而本次施工最大的难点就在于管道内部阴暗潮湿,空间细长,管径狭小,施工人员在管道内部甚至无法挺直腰背,只能保持跪姿或者侧躺进行施工,且管道内空气难以流通,连材料和工具也只能在管道外准备好后放在木板上靠绳索输送到施工人员身边,这对施工人员的技术和体力都无疑是一种挑战。

The sewage pipeline is located 5 meters underground, spans a total length of 60 meters, and has a diameter of just 0.7 meters. Its primary function is to connect the aeration biological tank and the UV disinfection tank at the wastewater treatment plant. After prolonged exposure to sewage and chemical flushing, the inner wall of the pipeline has developed numerous perforations and severe cavitation, with some areas already showing signs of water leakage. A complete pipeline replacement would require extensive excavation from scratch, consuming massive amounts of time, labor, and resources. Upon understanding the client's needs, our technical team visited the plant in early February to conduct an on-site inspection and equipment testing. The plant management recognized that our silicon carbide (SiC) pipeline anti-corrosion repair technology could effectively extend the pipeline's service life at a fraction of the cost of a full replacement.

Drawing on our extensive experience in repairing desulfurization pipelines at power plants, our technicians developed a customized repair plan tailored to the actual operating conditions of the sewage pipeline. Since the discharged wastewater contains high levels of chemicals that easily cause cavitation, and the pipeline has multiple perforations and leaks, direct repair was not feasible. Therefore, we adopted a two-step approach: "Leak Sealing First, Anti-Wear Protection Second." The greatest challenge of this project was the dark, damp, and confined environment inside the pipeline. The narrow space prevented workers from standing upright; they had to work on their knees or lying on their sides. Furthermore, poor air circulation meant that all materials and tools had to be prepared outside, placed on wooden boards, and hoisted in via ropes to reach the workers. This undoubtedly posed a significant test of both the technical skills and physical endurance of our construction team.

E_B7OTKDEPCB7T7B]VIYI{J.jpgQQ图片20230425141603.jpg

      石以砥焉,化钝为利,现场施工人员克服重重困难,分工明确,在保证自己的安全和健康的同时,仅仅用了十天时间,就完成了长达60米的管道修复任务。经过24小时的固化,管道就可以投入使用,大大缩短了客户的停机时间。而促成这次合作,不仅给客户带来了方便,更是弥补了我公司在污水行业管道修复方面的空白。

As the ancient Chinese proverb goes, "A whetstone hones the blade, turning the blunt into the sharp." Overcoming numerous challenges on-site, our construction crew maintained clear division of labor and strict safety protocols. In just 10 days, they successfully completed the repair of the 60-meter pipeline. After a 24-hour curing period, the pipeline was ready for operation, significantly minimizing the client's downtime. This successful collaboration not only brought great convenience to the client but also marked a significant milestone, filling the gap in our company's pipeline repair capabilities within the wastewater treatment industry.

QQ图片20230425141607.jpg04a8cbf2f54452ba023b2f23f1ddbf0.jpg